As a result of the growing concern with which we are all faced, we have made the decision to close all our construction sites with immediate effect. We believe that this is the only way to fully safeguard our employees, families and supply chain partners and their families. Please rest assured that business operations will continue as far as possible with all Rayner Rowen staff now working from home.

BUILDING A BETTER TOMORROW STARTS WITH YOUR ENVIRONMENT.

Call us 01257 221100

Thornleigh, Bolton

The works were split into Phases and consisted of the following:

Phase 1: Internal remodelling in converting existing accommodation on ground and first floor levels of Block 2 into Science and ICT Department including new Male & Female toilets. (Section 1)

Phase 2A: Internal remodelling in converting existing Science accommodation
of Block 6 into Performing Arts Department. (Section 2)

Phase 2B: Internal remodelling in converting existing IT accommodation on
ground floor of Block 9 into General Teaching Areas including new Male & Female toilets. (Section 3)

Phase 3: Conversion of Music Rooms within Block 7 into General Teaching Areas. (Section 4)

Project Name: Thornleigh, Bolton
Client: Board of Governors of Thornleigh Salesian College
Commencement: January 2019
Completion: October 2019
Duration: 40 Weeks
Value: 1.9 million